ENGENCO Moves to Strengthen Power Generation Ahead of Rainy Season
The Electricity Generation Company (ENGENCO) says it is strengthening its power generation capacity and putting measures in place to minimise disruptions during the forthcoming rainy season amid forecasts of an El Niño weather phenomenon.
ENGENCO Chief Executive Officer Engineer William Liabunya told The Malawi Guardian that the company had established a committee to develop and implement risk management strategies to address potential challenges associated with the anticipated weather conditions.
Liabunya said the company had restored 20 megawatts (MW) of generation capacity, including 7.4MW out of the 11MW lost at Nkula Power Station.
He said the remaining 3.7MW was expected to be restored to the national grid by Friday or Saturday.
He added that ENGENCO was working to ensure all its generation machines were operational and capable of meeting electricity demand during the rainy season.
To prevent interruptions caused by debris and silt carried by increased water flows, Liabunya said the company had also conducted maintenance works on major water intakes at Nkula, Tedzani and Kapichira power stations.
He further disclosed that ENGENCO had procured essential spare parts, with some already delivered for maintenance works at Nkula A. Additional consignments are expected towards the end of November or early December, while equipment for Wovwe Power Station is expected in January.
Liabunya said the interventions would improve the company’s preparedness to sustain electricity generation despite challenges associated with increased water flows during the rainy season.
Meanwhile, Chairperson of the Parliamentary Committee on Natural Resources Tiaone Hendry has urged ENGENCO and the Electricity Supply Corporation of Malawi (ESCOM) to ensure a reliable electricity supply, saying uninterrupted power remains essential for businesses and livelihoods.